Using Adjudication To Fight The Big Boys.
Sub-contractors experience increasing difficulties obtaining due payment
from main contractors. There are many complaints from small sub-contractors
that if they threaten litigation for recovery of sums due, they will
receive no more work.
Furthermore, most small sub-contractors cannot
afford the litigation costs and risks attached, in addition there
is the time factor in that litigation/disputes can take many months
or even years. It is in these circumstances that Alternative Dispute
Resolution (ADR) can be more effective.
Adjudication and arbitration are the most common
forms of ADR in the construction industry. Arbitration however, can
be just as costly and lengthy as litigation and this is where adjudication
can be a life saver to many aggrieved sub-contractors.
The right to adjudication arises in The Housing
Grants Construction and Regeneration Act 1996 and what a very important
right this is !!!
Previously ADR requested a consensual approach
in that both parties had to agree to settle their dispute by way of
existing arbitration, expert determination, conciliation and mediation.
Now however, Parliament has provided that construction contracts disputes
shall be subject to adjudication if either party wishes.
The benefits of adjudication to the sub-contractor
are great. The adjudicator must decide within 28 days of the referral
and this can be extended to 42 days by agreement. An adjudication
decision is binding on the parties. Generally the only way the decision
can be challenged is where the Adjudicator has acted outside his powers
or the dispute is otherwise decided by arbitration, litigation or
agreement.
The decision can be enforced by the Courts
upon application for summary judgment and in the event of non payment
by the paying party and upon further application, the Court may then
order recovery of sums due from the paying party’s bank accounts and/or
charges levied against assets such as property and shares.
A sub-contractor can therefore invoke the adjudication
right and obtain a quick decision while still on site. However, each
area of contention needs to be decided on its merits and in conjunction
with the drafting of the contract etc. Who pays for the adjudication
usually depends on the terms of the contract.
Most standard form contracts incorporate adjudication
rules which provide that the party’s cannot recover their own costs
in the adjudication. Neither party can claim any fees incurred by
lawyers, experts or anyone else who helps prepare his case. Both parties
are jointly and severally liable for the adjudicators fee in common
with the scheme, standard forms usually provide that the adjudicator
can decide who is to pay his fees and reasonable expenses by apportionment
between the parities in his decision.
Finally The Housing Grants Construction and
Regeneration Act 1996 provides that a construction contract must embody
eight principles concerning the right to adjudication (section 108).
If the contract does not comply with section 108 then the adjudication
provisions in the contract are ignored and the scheme applies.
The above applies to construction contracts
entered into after 1st May 1998.